< To Page 2 Gallery |
Page 3 |
|
The next stage of the formation requires a large horse shoe cutting leading around to an 18 metre long trestle bridge. |
The next boulder being planted in the ground to form on of the abutments for the trestle bridge. |
Looking down on the new cutting. |
Track panels for the next section ready to go. |
Laying out the new panels in the horse shoe cutting. |
Looking back across the gap that the trestle bridge will span
|
The curve radius is checked and the second rail is clamped in position
ready for welding
|
Track laying progressing
|
Not much work going on here!!!
|
Work starts on the formation on the bottom side of the trestle bridge
site
|
Grading the batter on the bank
|
Looking down over the horse shoe curve
|
Work commences on the turn table main beam in the CNC mill
|
Machining work completed
|
Welding on the deck support beams
|
Track and hand rails are fitted
|
Rolling the circular rail for the turntable wheels to run on
|
The turntable is lowered onto the 2½" diameter pivot ball
|
Stabiliser wheels are welded into position
|
Timber deck being fitted
|
Brick work taking shape
|
The almost completed turntable
|
The track work reaches the turntable and the first loco is turned
|
Turning the first loco on the turntable
|
Video:
Turning a loco
|
Work commences on the trestle bridge with the trestle pier holes bored
|
Concrete trestle footings are completed and the bridge abutments are cut out to locate the timber beams
|
One of six steel trestles for the bridge
|
Steel base plates were cast into the concrete footings to allow the trestles to be welded to
|
The last of the trestles is welded in place
|
The 34 metre radius curve in the trestle bridge can be clearly seen
|
Looking down over the bridge under construction
|
The first of the bridge timbers are bolted in place
|
The change in elevation on the BCT can be clearly seen
|
The bridge is almost ready for the decking
|
Looking down the 1 in 43 grade over the bridge
|
It is really starting to look like a bridge!
|
The decking is complete leaving only the track work and some handrails to be fitted
|
Posts bolted on and the handrails are taking shape
|
The completed structure awaiting the track work and a coat of paint
|
The track gang hard at it laying the rails across the bridge
|
Note the difference in elevation between the trestle bridge and the track rounding the workshop
|
A work train with a carriage load of new track panels crosses the bridge
|
Track across the bridge is complete and a train crossing the bridge
|
The next section of the formation is almost complete and ready for the track
|
The slight climb up through the cutting from the lowest point on the track
|
The bottom reversing loop will be located amongst the trees in the background to the right of the excavator
|
Looking up the 1 in 70 grade the excavator is about half way through the cutting
|
Installing a passing loop before rounding the bottom corner at the lowest point on the railway
|
Welding continues . . .
|
Looking back though the cutting, the train is sitting at the lowest point on the railway
|
Looking up through the cutting, the bottom reversing lop will be situated amongst the trees behind the loco and track gang
|
The track shown here through the cutting is the flattest section on the entire railway
|
The track shown here through the cutting is the flattest section on the entire railway
|
The cutting through the bottom reversing loop has been made wide enough to accommodate a couple of tracks for a station area
|
The formation for the bottom reversing loop is just about ready for track laying
|
Track laying has almost reached the bottom loop!!!
|
|
|
|
< To Page 2 Gallery |
Page 3 |
|